Project Team to visit the lighthouse this week on or about Nov 12 2007 The team is prepared to enter the tower on this trip.
The climbing experts will scale the inside of tower to replace the safety line to the top of the tower. This line is made fast for usage with their climbing harnesses by the rest of the team when climbing the tower as a safety rope.
Other team members will excavate the weight well at the bottom of the tower. The excavation will examine the well for evidence of settlement cracks. The tile floor will be exposed in several areas and also examined for cracking. The present condition of the floor and weight well will be documented for future use. Another group of the team will be inspecting the exterior of the structure as part of the bidding of the repair project that is underway to fix some of the damage near the bottom of the lighthouse.